Limited Liability Partnership "Batys Power" was formed in 2011, commissioning of the first start-up complex took place on March 31, 2016.

The territory and engineering infrastructure of GTPP-200 URALSK, that was performed during the construction of the first start-up complex, was prepared for the installation of two turbine-generator units with the subsequent construction of heat-recovery units and generation of additional power.

Management

General Director - Marina Balashova

Stages of GTPP-200 URALSK construction. First start-up complex with a capacity of 100 MW.

January 2014 - beginning of construction.

December 2014 - the project is included in Industrialization Map of the Republic of Kazakhstan.

December 2015 - The head of the Country, during the nationwide teleconference, gave start to the beginning of GTPP-200 URALSK, First start-up complex 100 MW commissioning.

April 2016 - putting into commercial operation.