First start-up complex
GTPP-200 Uralsk. First start-up complex.
General parameters of GTPP:
- Rated output of the plant is 100 MW
- Plant capacity is 700 million kW/h per year.
- Consumption of fuel gas is 270 million cubic meters per year.
- Total number of employees is 63
Turbine generator unit - GE FRAME 9E,”Nuovo Pignone”, Italy:
- Gas Turbine: Type MS 9001 E.;
- Generator: Type T230-268 GEC Alstom.
Modern equipment from world leaders in the field of electric power engineering, maintenance is carried out by the company Ethos Energy, Germany.